Residents and stakeholders in Osun State have raised the alarm over the alleged abandonment of the Ilesha–Eti Oni road construction project despite more than ₦3 billion reportedly paid to three construction companies in December 2025.
The companies identified as beneficiaries of the payments are Sail Through Construction Ltd, Ottman Construction Ltd and Medaville Construction Ltd, reportedly engaged to execute the road project.
Findings from project tracking indicate that construction work has stalled since April 2026, leaving the road in a deplorable condition and raising serious questions about the utilisation of the funds released for the project.
Although some work was reportedly carried out, including the construction of drainage channels on both sides of critical sections of the road, tunnels, grading and the laying of granite, the project remains incomplete.
Some sections of the road reportedly still have loose granite yet to be properly spread, while other critical areas remain unattended.

The situation has triggered complaints among residents and road users, who say the abandoned construction work has made travelling along the route increasingly dangerous.
Residents have lamented the deplorable state of the road, alleging that several accidents have occurred as a result of its poor condition.
Stakeholders are now demanding urgent intervention from the Federal Ministry of Works (FMW), the implementing agency, insisting that Nigerians deserve a clear explanation of what has happened to the project.
They are also calling on the ministry to disclose the total amount released, the specific scope of work awarded to each contractor, the level of completion, the reasons for the reported stoppage and the expected date of completion.
The reported payment of over ₦3 billion for a project that has remained stalled for months raises legitimate questions about accountability, contract supervision and value for public money.
For residents who depend on the road daily, the issue goes beyond figures and official paperwork. Their safety, livelihoods and access to neighbouring communities are at stake.
The Federal Ministry of Works and the three contractors must provide answers. Public infrastructure projects are funded with taxpayers’ money, and Nigerians deserve completed roads, not abandoned construction sites and unanswered questions.